A garage conversion ADU in Florence-Graham typically runs $45,000 – $130,000 and takes three to five months from permit submittal to final inspection, depending on how much plumbing, electrical and structural work your detached garage needs. The most common version here turns a 1920s – 1950s single-car or two-car garage into a 400 – 600 square foot studio or one-bedroom unit with a kitchenette and full bath. Call (833) 842-7204 to schedule a free on-site estimate.
How a Garage Conversion ADU Comes Together, Stage by Stage
Every Florence-Graham garage conversion we build follows the same sequence. Here’s what actually happens and when.
- Stage 1, feasibility and survey (days 1 – 7). We measure the existing garage, check the slab, look at the roof structure and note where the electrical panel and water main sit. You decide at this point whether the unit will be a studio or one-bedroom, and whether the garage door opening gets framed in or kept as a code-compliant egress door. We also confirm the setback picture on your lot, which matters more than people expect on Florence-Graham’s narrow parcels.
- Stage 2, plans and permit submittal (weeks 2 – 8). Drawings get prepared and submitted to LA County Public Works, since Florence-Graham is unincorporated. You review and sign off before submittal. Plan check can take four to eight weeks depending on corrections the County sends back. This is the longest stretch where you’re waiting rather than working, so we push it forward early.
- Stage 3, demolition and rough-in (weeks 2 – 4 of construction). The old garage door, tracks and opener come out, and any damaged drywall or siding goes. Then the trades run new: plumbing for the bathroom and kitchenette, a dedicated electrical subpanel if the main panel allows it, insulation and framing for the new partitions. You choose fixture locations and outlet placement during this window. County inspectors check rough framing, rough electrical and rough plumbing before any wall closes.
- Stage 4, finishes and systems (weeks 5 – 9). Drywall, paint, flooring, cabinets, countertops, the bathroom tile and fixtures, and a mini-split or through-wall HVAC unit sized for the square footage. This is where material grade shows up and where you’ll make the most decisions.
- Stage 5, final inspection and handoff (week 10 – 14). Final building, electrical, plumbing and mechanical inspections, then a walkthrough with you. We hand over the signed-off permits and warranty paperwork. If anything on the punch list isn’t right, it gets fixed before we call it complete, backed by our 730-Day Done Right Promise.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between for a Garage Conversion ADU
Most of the cost difference between two Florence-Graham garage conversions comes down to a handful of decisions. Here’s the honest trade-off on each.
- Slab or raised floor. Reusing the existing slab is the cheapest and fastest path, and the area’s minimal frost makes it viable. If the slab is cracked (expansive clay under parts of the neighborhood does that), a raised subfloor adds cost but keeps plumbing runs cleaner and the floor warmer.
- Full kitchen vs. kitchenette. A full range and sink need more circuit and venting. A kitchenette with a cooktop and under-counter fridge costs less and suits a studio unit. You decide this early because it drives the electrical plan.
- Roof approach. Many of these detached garages have flat or low-slope roofs that have baked under decades of South LA sun. Patching is possible, but a full tear-off with a reflective low-slope membrane (Atlas and Tamko both make products suited to this climate) adds years of life and puts the lid on a finished unit rather than over a tired one.
- Windows and doors. Off-the-shelf vinyl sliders keep budget down. If you’re building for a long-term tenant or family member, an impact-rated option from PGT or a similar line gives better security and heat control. This is where the brand choice genuinely matters, not just the label.
- Bath and finishes grade. A prefab shower surround and stock vanity land at the bottom of the range. Tile and a custom vanity push toward the top. Neutral, durable finishes rent and resell better than trend pieces.
What a Garage Conversion ADU Costs in Florence-Graham, CA

The realistic range for a garage conversion ADU in Florence-Graham is $45,000 to $130,000. A simple studio reusing the slab and existing panel lands near $45,000 – $65,000. A one-bedroom with a full kitchen, upgraded bath, new roof and a new electrical subpanel climbs toward $100,000 – $130,000.
| Line item | Typical range |
|---|---|
| Demolition, framing, drywall | $8,000 – $18,000 |
| Plumbing (bath + kitchenette) | $6,000 – $14,000 |
| Electrical + subpanel | $5,000 – $12,000 |
| HVAC (mini-split or through-wall) | $3,500 – $8,000 |
| Bath finishes and fixtures | $5,000 – $12,000 |
| Kitchen / kitchenette | $4,000 – $14,000 |
| Flooring, paint, trim | $3,000 – $8,000 |
| Roof repair or replacement | $3,000 – $16,000 |
| Permits and plan check | $2,500 – $6,000 |
Five things push a Florence-Graham job to the low or high end: unit size, whether the panel can take the added load, whether plumbing has to be trenched under slab, roof condition, and finish grade. A written line-item estimate includes all of the above plus permits. It typically excludes landscaping, site drainage upgrades and any foundation repair found once the slab is exposed. The number on the estimate is the number you pay, and there are no change orders unless you approve them.
See the difference
Before
After
Before
After
Before
AfterWhat Florence-Graham’s Housing Stock Does to This Job
Florence-Graham is unincorporated LA County, which means permits go through LA County Public Works rather than the City of LA. That single fact trips up contractors who only work inside city limits, and garage conversions to habitable space are the most common permit pulled in ZIP 90001. The housing stock drives the rest. Those 1920s – 1950s single-story stucco and wood-frame bungalows sit on 5,000 – 6,000 square foot lots with narrow side yards, and their detached garages were built to park a car, not to meet today’s energy and egress code. We regularly find garages where the slab is cracked from clay soil movement, the wiring predates a grounded panel, and the roof has never had more than a patch. Those aren’t dealbreakers, just line items, and a good estimate accounts for them up front. Many homeowners here pay cash and want a crew that can walk them through the permit process in Spanish, which we plan for from the first visit.
Serving Florence-Graham, CA – Our Local Coverage Area
We serve Florence-Graham and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked About Garage Conversion ADU in Florence-Graham

Expect about three to five months from submittal to final inspection, with County plan check typically taking four to eight weeks and construction running two to three months after that. Call (833) 842-7204 for a timeline specific to your garage.
Yes. Because Florence-Graham is unincorporated LA County, the permit and inspections go through LA County Public Works, not the City of LA. We prepare and submit the drawings and pull the permits, and we don’t move forward until the County signs off on each stage.
Sometimes. If the existing garage is close to the main house’s water and drain lines and the panel has capacity for a subpanel, we keep rerouting minimal. Most conversions still need a bath and kitchenette with new drains, so some plumbing work is almost always part of the job.
The range is $45,000 to $130,000, with the low end covering a studio that reuses the slab and existing systems and the high end covering a one-bedroom with a full kitchen and new roof. Our written estimate breaks it down line by line, and 0% financing for 18 months is available.
Every conversion is covered by the 730-Day Done Right Promise, one of the longest workmanship guarantees in residential construction. If something isn’t done right, we make it right, and you get the signed-off inspection paperwork at handoff.
Get a Free Estimate for Your Garage Conversion ADU in Florence-Graham
If you’re ready to price a garage conversion ADU in Florence-Graham, call (833) 842-7204. We’ll schedule a free on-site visit, check your garage, lot and panel, and hand you a written line-item estimate with a real timeline. Calls are answered by a live person around the clock. You’ll also get the free design consult and $1,000 off projects over $10,000 by request.
Written by the team at Groundwork Construction Co. of Inglewood.